When an unforeseen underground utility conflict, a late owner-furnished equipment delivery, or a structural design bulletin stops work on a controlling area of your project, writing a two-paragraph letter asking for fourteen extra calendar days rarely works. Owner representatives and construction managers reject narrative-only extension requests on sight because the contract requires proof that the delay pushed the critical path.
Picture the monthly change-order review meeting. Your project manager knows a late RFI response held up steel erection in Area B for three weeks, and costs are mounting. Without a clean Time Impact Analysis (TIA) tied to the last accepted schedule update prior to the event, the owner's scheduler argues that Area B had twenty-two days of float and denies both time and general conditions. Meanwhile, hiring a forensic claims boutique often starts at $15,000 to $35,000, pricing mid-market contractors out of defending valid change orders.
This 2026 guide explains how a defensible Time Impact Analysis is built in Primavera P6 or Microsoft Project, breaks down our published $1,800 to $3,500 TIA rate and $2,500 to $5,000 recovery planning rate, and shows you how to verify your update file before submitting to the owner.
2026 Time Impact Analysis and Recovery Pricing Breakdown
Not every schedule delay requires a fifty-page forensic report. Most active construction and capital projects need a clean, spec-compliant fragnet inserted into the contemporaneous schedule update, a before-and-after critical path comparison, and a concise written narrative supporting a contract modification.
| Scope Type | Published 2026 Price | Typical Turnaround | What Is Included | Best For |
|---|---|---|---|---|
| Pre-TIA 48-Hour Schedule Health Check | $750 flat | 2 business days | Audit of the contemporaneous update file for open ends, out-of-sequence progress, and float anomalies before fragnet insertion | Checking whether your current XER or MPP file will survive owner scrutiny before you submit a TIA |
| Schedule Working Review (Paid Brief) | $897 flat | 3 to 5 business days | Principal-reviewed written brief diagnosing critical path shifts, baseline variance, and recommended next steps | Owners or contractors who need an objective readout on a disputed baseline or update |
| Single-Event Time Impact Analysis (TIA) | $1,800 to $2,400 | 5 to 7 business days | One discrete delay fragnet inserted into the last accepted update, before/after critical path comparison, native XER/MPP, and TIA narrative | Clear change directives, late RFI/submittal responses, or unforeseen site conditions affecting one work path |
| Multi-Event or Complex TIA Package | $2,500 to $3,500 | 7 to 12 business days | Multiple linked fragnet activities, pacing/concurrency check across near-critical paths, variance tables, and full modification narrative | Complex bulletins, multi-trade utility or phasing impacts, or stacked owner directives |
| Recovery or Resequence Planning | $2,500 to $5,000 | 5 to 10 business days | Re-logic, crew/phasing overlap modeling, milestone recovery validation, and native XER/MPP recovery submittal | Projects that need to pull a slipping completion date back on schedule without manufacturing fake durations |
The 5-Step Process That Makes a TIA Pass Owner Review
Owner schedulers reject TIAs for predictable technical reasons: the contractor used the wrong monthly update as the starting point, tied the fragnet directly to the project finish milestone with a finish-to-start link to force a delay, or ignored out-of-sequence logic in the underlying file. Every CDM Suite TIA follows five strict steps:
| Step | Technical Action in P6 / MS Project | Why Reviewers Check This |
|---|---|---|
| 1. Select the Contemporaneous Update | Lock the last accepted schedule update immediately preceding the start of the delay event | Proves the project status and critical path position as they actually existed when the impact hit, not with hindsight |
| 2. Hygiene Check on the Unimpacted File | Verify that retained logic / progress override settings, data date, and open ends are clean before adding new activities | Prevents the owner reviewer from dismissing the TIA on a technicality unrelated to the delay event |
| 3. Build and Insert the Fragnet | Model the discrete delay steps (notice, RFI/redesign, procurement, field execution) with realistic durations and calendars | Breaks a vague delay claim into verifiable, field-grounded activities |
| 4. Tie into the Existing Network and Recalculate | Link the fragnet to the exact predecessor and successor activities affected by the change and run the schedule calculation (F9) | Demonstrates objectively whether the event consumed existing float or pushed the controlling critical path |
| 5. Document Variance and Concurrency | Export before-and-after Gantt comparisons, float consumption tables, native XER/MPP files, and a plain-English narrative | Gives the contracting officer or owner representative a complete package they can sign off on |
Why Monthly Update Discipline Is the Cheapest TIA Insurance
The hardest TIA to win is one built on top of a schedule that has not been updated properly in four months. When actual start and finish dates are missing or out-of-sequence logic is left unresolved, reconstructing the contemporaneous critical path takes twice the effort.
Contractors who use our $950 per month schedule update cycle keep a clean, review-ready archive of every monthly XER or MPP file. When a change event hits, the contemporaneous baseline is already verified and a TIA can be turned around in days rather than weeks.
Need a fast readout on an active delay or recovery request? Start with a $897 Schedule Working Review, check our 48-Hour Schedule Health Check ($750), or book a project scheduling consultation to scope a $1,800 to $3,500 TIA.
Order a Schedule Working Review ($897) to evaluate your current XER or MPP file, or book a consultation to scope a $1,800 to $3,500 TIA or $2,500 to $5,000 recovery plan.
Frequently Asked Questions
How much does a Time Impact Analysis (TIA) cost at CDM Suite in 2026?
Published Time Impact Analysis rates at CDM Suite run $1,800 to $3,500 depending on the number of delay events (fragnets), the condition of the contemporaneous schedule updates, and the narrative detail required by your contract specification.
What if the owner requires a recovery or resequence schedule alongside the TIA?
Recovery or resequence planning at CDM Suite runs $2,500 to $5,000. We model practical logic adjustments, crew or shift overlaps, and procurement acceleration so your team can see whether the slip can be mitigated or requires a formal contract time extension.
What if our last monthly schedule update has broken logic or negative float before we insert the TIA fragnet?
Inserting a delay fragnet into a schedule with broken logic or unaddressed out-of-sequence progress is the number one reason owners reject a TIA. We can run a 48-Hour Schedule Health Check ($750 flat) or a Schedule Working Review ($897) first to verify the baseline and contemporaneous update file before modeling the impact.
Does CDM Suite provide courtroom expert-witness testimony?
No. CDM Suite provides project-level CPM scheduling, contemporaneous Time Impact Analysis ($1,800 to $3,500), and recovery planning ($2,500 to $5,000) to get change orders, time extensions, and recovery sequences resolved at the project table before disputes escalate into litigation.