Schedule Health Check — Sample Excerpt
Redacted for a CM team · Project Scheduling diagnostic
Health score
Overall schedule health: 68/100 — usable for internal tracking, not yet owner-ready.
Critical issues: missing logic ties on façade package, negative float on milestone M-104 without recovery narrative.
DCMA-style flags
- Missing predecessors on 4 finish activities
- High float on non-critical paths masking slip risk
- Update notes absent for last two biweekly cycles
90-day cadence recommendation
- Biweekly updates with mandatory variance comments
- Owner summary: 1-page milestone + 2-week look-ahead
- Optional Schedule Sprint: baseline cleanup + two update cycles ($2,500)